Site Feasibility Study: What to Check Before You Buy Commercial Land in Texas

Undeveloped flat land behind an old barbed wire fence, with overhead power lines crossing the tract

Raw land looks simple from the fence line. Feasibility work finds what you can't see from here: floodplain, soil, utility capacity and the easements under those power lines. (Photo: Photo by Christopher Castleberry (@thealphaboy7) on Unsplash · Unsplash License)

A site feasibility study answers three questions before you close on land: can you build what you have in mind here, what will the site itself add to the cost, and which approvals stand between you and a permit. Most of the expensive surprises on a commercial site (floodplain, no sewer, an outfall that doesn't exist, a plat that has to be redone) are findable during the due-diligence period if someone goes looking.

This is the engineering side of feasibility. Market studies, pro formas and zoning strategy matter too, but they assume the dirt cooperates. Here's what an engineer checks, where the information comes from, and what a red flag usually means.

What an engineering site feasibility study covers

ItemWhere the information comes fromRed flagWhat it usually means
FloodplainFEMA Flood Insurance Rate Map, local floodplain administratorAny part of the buildable area in a mapped flood zone or floodwayFloodplain permit, elevated pads, possibly a flood study; floodway may be off-limits
SoilsUSDA Web Soil Survey for screening, then a geotechnical investigationHigh shrink-swell clay, shallow rock, fill of unknown originDeeper or stiffer foundations, subgrade treatment, rock excavation
Drainage outfallTopographic survey, aerials, city drainage mapsNo defined outfall, or runoff that has to cross a neighborDrainage easement needed, detention, offsite improvements
DetentionLocal drainage criteria (many North Texas cities use NCTCOG iSWM)Detention required with little spare landLost acreage or underground storage
Water and sewerUtility provider maps and a capacity letterSewer main far away or too shallow, low fire flowLine extension, lift station, booster, or a different site
AccessCity or TxDOT driveway rules, traffic countsFrontage only on a state highway, driveway spacing limitsTxDOT permit, turn lanes, shared access
PlattingCity or county plat recordsTract is unplatted or the plat doesn't match the planPlatting or replatting before building permits
EasementsTitle commitment and boundary surveyPipeline, power or drainage easement through the building areaSite plan rework, relocation cost and delay
TopographySurvey or LiDARSteep grades, big cut or fillEarthwork cost, retaining walls
Construction stormwaterTCEQ construction general permitOne acre or more of disturbanceSWP3 and best management practices for construction

Floodplain: can you build in a flood zone?

Often yes, with conditions. FEMA's flood maps show the Special Flood Hazard Area, which FEMA defines as land with a 1% or greater chance of flooding in any given year. The official maps are on FEMA's Flood Map Service Center.

Communities in the National Flood Insurance Program have to require permits for all proposed construction or other development in flood-prone areas (44 CFR §60.3). Inside a mapped regulatory floodway, encroachments are prohibited unless an engineering analysis shows they won't increase flood levels. In practice that means the floodway portion of a tract is usually treated as unbuildable, and the rest of the floodplain needs a permit and elevated construction. Local rules are often stricter than the federal minimum, so check with the city or county floodplain administrator early.

Soils: screen online, confirm with borings

The USDA Web Soil Survey is a good first look. It shows mapped soil units with ratings for shrink-swell potential, depth to bedrock and suitability for buildings. In much of North Texas it will show highly plastic clay. That tells you to expect foundation design for expansive soil, but it is mapped at a scale meant for planning, not for designing a specific building.

For a commercial purchase, a preliminary geotechnical investigation with a few borings is usually worth doing inside the due-diligence period. It tells you the likely foundation type, whether subgrade treatment will be needed under pavement, and whether there's rock or groundwater close to the surface.

Drainage, detention and the outfall question

Every site has to send its runoff somewhere. The questions are where, how much, and through whose land. If the natural outfall crosses a neighbor's property with no drainage easement, you may need to buy one or build a pipe to a public system. Many cities in North Central Texas base their drainage criteria on NCTCOG's integrated Stormwater Management (iSWM) program, but local adoption and amendments vary, so read the city's own criteria manual.

Utilities: get it in writing

"Utilities available" on a listing means little. Ask the provider for a capacity or availability letter. For sewer, check the depth of the nearest main, because a gravity line that can't reach it means a lift station. For water, check fire flow, since a commercial building's sprinkler and hydrant demand can exceed what an older line delivers.

Access and platting

If the only frontage is on a state highway, a new or modified driveway needs a TxDOT access permit, and TxDOT's Access Management Manual governs spacing and design. In some cities that authority has been transferred to the city.

Platting is the other common hold-up. Under Texas Local Government Code §212.004, an owner who divides a tract within a city or its extraterritorial jurisdiction to lay out lots or streets generally has to have a plat prepared and recorded. Outside city limits and the ETJ, county subdivision rules apply. If the tract is unplatted or the existing plat doesn't fit your plan, budget the time for platting before building permits. Plats are prepared by a registered professional land surveyor; the civil engineer prepares the infrastructure plans that go with them.

Desktop study versus field study

Desktop feasibilityField-verified feasibility
InputsPublic maps, aerials, utility maps, plat and title records, Web Soil SurveyAdds a boundary and topographic survey, preliminary borings, utility locates, meetings with the city
Good forScreening several sites, early go/no-goA site you're serious about, before the due-diligence period ends
Typical outputConstraints memo with flagged risksConstraints map, approvals list, conceptual grading and utility routes

Start with a desktop study when you're comparing sites. Move to field verification on the one you intend to buy.

A short pre-closing checklist

  • Pull the FEMA flood map panel and talk to the floodplain administrator.
  • Run the tract through Web Soil Survey, then schedule preliminary borings.
  • Confirm the drainage outfall and whether detention is required.
  • Get water and sewer availability letters with capacity.
  • Check driveway options with the city and, if applicable, TxDOT.
  • Confirm plat status and any replat requirements.
  • Review the title commitment for easements, and plot them on the survey.
  • Estimate earthwork from the topography.
  • Note TCEQ construction stormwater requirements if you'll disturb an acre or more.

Talk to Isbell Engineering Consultants about a site before you buy

Isbell Engineering Consultants lists site feasibility and due diligence among its civil engineering services: preliminary evaluation of proposed sites, review of drainage, utilities, access, grading and infrastructure constraints, and early engineering input before acquisition. Preliminary borings and foundation recommendations come from our geotechnical engineering services. If you have a tract under contract or under consideration, contact us with the address, your intended use and your due-diligence deadline. The full list is on our services page.

Frequently asked questions

What is a site feasibility study?

It's an early evaluation of whether a specific piece of land can support a planned project, and at what cost. The engineering portion looks at floodplain, soils, drainage, utilities, access, platting, easements and topography, then lists the constraints and the approvals needed.

How do I know if land is buildable?

Check the flood map, soil conditions, access to a public road, availability of water and sewer (or septic suitability), plat status and recorded easements. If those line up with your intended use, the land is likely buildable. A feasibility study puts those checks in one place.

Can you build in a flood zone in Texas?

Often, with a floodplain development permit and construction that meets the community's elevation requirements. Building in a mapped regulatory floodway is much harder because encroachments can't raise flood levels. Your local floodplain administrator sets the specific rules.

Do I need a geotechnical report before buying land?

It isn't legally required to buy, but a preliminary geotechnical investigation during due diligence can reveal expansive clay, shallow rock or poor fill that change foundation and paving costs. For commercial land, it's often worth the modest upfront cost compared with finding out after closing.

How long does a site feasibility study take?

A desktop study can be quick. A field-verified study depends on survey, drilling and utility response times. Tell your engineer your due-diligence deadline at the start so the scope fits the time you have.

Sources

  1. FEMA, Flood Maps
  2. 44 CFR §60.3, Flood plain management criteria for flood-prone areas (Cornell LII)
  3. Texas Local Government Code §212.004, Plat Required (FindLaw)
  4. TCEQ, Stormwater General Permit for Construction Activities (TXR150000)
  5. TxDOT Access Management Manual, Driveway Permits, Design, and Materials
  6. NCTCOG iSWM Technical Manual
  7. USDA NRCS Web Soil Survey

Image credits