A steel trench box, often called a shoring box. Strictly it's a shield: it protects workers if the trench walls fail, while true shoring pushes back on the walls to stop them failing. (Photo: Jwh, CC BY-SA 3.0 lu, via Wikimedia Commons · CC BY-SA 3.0 lu · cropped and resized)
Shoring in construction is temporary support. It holds back the sides of a trench or excavation, holds up formwork and fresh concrete, or props an existing structure while work goes on around it, and it comes out once the permanent structure or backfill takes over. Who may design it depends on depth, soil and what sits next to the hole.
The word covers three different jobs that share one idea, a temporary member carrying load until something permanent can:
On a trench job, keep shoring and shielding apart. Shoring is designed to stop a collapse. Shielding, such as a trench box, only protects the workers inside it when a collapse happens. OSHA treats them as separate kinds of protective system with separate rules.
| Type | What it holds | Typical use | Design route |
|---|---|---|---|
| Timber trench shoring | Trench walls | Shallow utility trenches | OSHA Appendix C tables, trenches up to 20 ft deep; otherwise an engineer |
| Hydraulic (aluminum) shoring | Trench walls | Utility trenches, quick installs | Manufacturer's tabulated data; OSHA Appendix D if that data can't be used |
| Trench shield (trench box) | Workers, not the walls | Pipe laying in open ground | Manufacturer's tabulated data |
| Soldier piles and lagging, sheet piles | Excavation faces, adjacent ground | Basements, deep utility work, cuts next to buildings | Project-specific engineered design |
| Soil nailing | Excavation faces and slopes | Deeper cuts with room for nails behind the face | Project-specific engineered design |
| Post shores and reshores | Formwork, fresh concrete, young slabs | Elevated slabs, beams, transfer girders | Formwork drawings; tiered single post shores need a qualified designer |
| Raking shores | Existing walls | Renovation, demolition next door | Project-specific engineered design |
Tabulated data covers the common cases. A job that falls outside it needs a design for that site.
Under §1926.652(a)(1), each worker in an excavation must be protected from cave-ins by an adequate protective system. There are only two exceptions: the excavation is entirely in stable rock, or it's less than 5 feet deep and a competent person has examined the ground and found no sign of a potential cave-in. A trench under 5 feet still needs protection if that examination finds signs of trouble.
For support systems, shields and other protective systems, §1926.652(c) gives the employer four design options:
| Option | Basis of design | Limits |
|---|---|---|
| 1 | OSHA Appendices A and C (timber), D (aluminum hydraulic) | Appendix C covers trenches up to 20 ft deep |
| 2 | Manufacturer's tabulated data | Follow every limit; deviations need the manufacturer's written approval, kept on site |
| 3 | Other tabulated data | Must be in writing, list its limits, and be approved by a registered professional engineer |
| 4 | Design by a registered professional engineer | Written plan with sizes, types and configuration of materials, plus the engineer's identity, kept at the jobsite |
The sloping tables in Appendix B are written for excavations 20 feet deep or less. Deeper than that, or outside what any table covers, the design comes from a registered professional engineer.
Several other rules in §1926.651 shape a shoring plan:
OSHA's Appendix A sorts soil into stable rock, Type A, Type B and Type C. Type A is cohesive soil with an unconfined compressive strength of 1.5 tons per square foot or more, and clay is the textbook example. On paper, a stiff North Texas clay looks like Type A.
But no soil is Type A if it's fissured, if it's subject to vibration from heavy traffic or pile driving, or if it has been previously disturbed. Expansive clays crack as they dry, so a cut in high-plasticity clay often shows fissures. Old utility corridors are disturbed ground. Under Appendix A, submerged soil or soil with water freely seeping from it is Type C.
Soil type sets the allowable slope and the timber sizes. Appendix B allows a maximum simple slope of 3/4:1 in Type A soil and 1:1 in Type B, for excavations 20 feet deep or less. Type C soil gets 1½:1 under §1926.652(b)(1). Moving from A to C can double the width of a sloped cut, which is often why a site with tight property lines ends up with shoring instead of slopes.
A geotechnical report with soil borings gives the shoring designer strengths, water levels and layering. When the cut goes below groundwater, shoring and dewatering have to be designed together.
Digging beside a building brings in the building code too. Under the 2021 IBC (check which edition your city enforces):
OSHA adds its own line under §1926.651(i)(2). Digging below the base of a footing or retaining wall, where that could reasonably endanger workers, isn't allowed unless there's a support system such as underpinning, the excavation is in stable rock, or a registered professional engineer has approved the determination that the structure is far enough away or the work won't create a hazard.
A basement or deep utility cut along a property line therefore needs an engineered design and a monitoring plan before digging starts.
Shoring for concrete operations falls under 29 CFR 1926.703:
The engineer of record usually sets stripping criteria and allowable construction loads. The shoring layout is often a delegated design by the contractor's engineer, reviewed as a submittal.
Texas has a specific rule for public work. Under Health and Safety Code §756.023, when a project for a political subdivision includes trench excavation deeper than 5 feet, the bid documents and contract must include:
The owner may also require a prebid conference to coordinate a geotechnical investigation by bidders.
Isbell Engineering Consultants lists temporary structures design, covering shoring, scaffolding and formwork systems, among its structural engineering services. Its geotechnical engineering services include site investigations, earth retaining wall soil parameters for gravity, cantilevered and anchored walls, and groundwater and dewatering design. If you have an excavation, a cut next to an existing building or a cast-in-place structure that needs a shoring design or review, send the project details through our contact page.
Temporary support for excavation walls, formwork and fresh concrete, or an existing structure, removed once the permanent work or backfill takes the load.
Shoring holds the trench walls up. A shield, such as a trench box, protects the workers inside it if the walls fail. OSHA regulates both under 29 CFR 1926.652.
When the system isn't taken from OSHA's appendices or the manufacturer's tabulated data. OSHA's timber shoring and sloping tables stop at 20 feet, so deeper excavations need an engineered design.
Shores installed as the original forms and shores come out, so young concrete isn't loaded beyond its capacity. OSHA 1926.703 requires it whenever that would otherwise happen.
Often yes. The IBC requires affected footings to be underpinned or protected, and a retention system protecting adjacent structures needs a registered design professional and a monitoring plan. Check with your local building department.