Reinforcing for a mat foundation before the pour. The column cages tie the frame above into the mat, which spreads the building load over the whole footprint. (Photo: Photo by Toni Reed (@trfotos) on Unsplash · Unsplash License)
Foundation design is the process of matching what a building pushes down (and sideways, and sometimes up) to what the ground underneath can take. On a commercial project it's a two-engineer job: the geotechnical engineer works out how the soil and rock behave, and the structural engineer designs the concrete and steel that sit in that ground. On North Texas clay, the hardest part usually isn't carrying the weight. It's dealing with soil that swells when wet and shrinks when dry.
Here's how the process runs, how the foundation type gets chosen, which parts of the building code drive it, and what an owner should send and check along the way.
Every project is different, but the sequence is close to this:
The handoff in steps 3 and 4 is where most foundation problems are either prevented or baked in.
| Task | Geotechnical engineer | Structural engineer |
|---|---|---|
| Building loads and load combinations | Uses them to size the investigation | Calculates them (ASCE 7 and the IBC) |
| Borings, sampling, lab testing | Plans, logs and interprets | Reviews the results |
| Allowable bearing pressure and settlement | Sets them | Designs to them |
| Swell potential and active zone on clay | Estimates them and the design parameters | Designs slabs and beams for them |
| Foundation type | Recommends what the ground supports | Chooses the system with the owner and architect |
| Footing, slab, pier and pile sizing and reinforcing | Gives depth, capacity and side-friction values | Designs the elements |
| Pad preparation, fill, moisture conditioning | Specifies it | Coordinates it with the slab design |
| During construction | Checks bearing soils, pier holes, fill placement | Answers RFIs, reviews submittals, observes the work |
When both disciplines sit in the same firm, or at least talk early, the foundation is usually simpler and cheaper. When the report is ordered late and the structure is already drawn, the foundation tends to get whatever is left.
Section 1803 of the 2021 International Building Code covers geotechnical investigations. The building official can require one, and you need one any time the design uses bearing values higher than the code's presumptive values. Table 1806.2 allows only 1,500 psf vertical bearing for clays and silts (CL, ML, MH and CH) without a report. That is low for most commercial buildings, so in practice nearly every commercial project in North Texas starts with borings.
Section 1803.5.3 sets the test for expansive soil. Under the IBC, soil counts as expansive when it has a plasticity index of 15 or more, more than 10 percent passing the No. 200 sieve, and more than 10 percent of particles smaller than 5 micrometers; an expansion index above 20 is an alternative test. When the borings show clay that meets that definition, which is common on North Texas sites, Section 1808.6 applies.
IBC §1808.6 gives four routes for building on expansive soil: design the foundation to resist the soil's volume change (including taking it below the zone of seasonal moisture change), design a slab-on-ground to the WRI/CRSI or PTI methods, remove the expansive soil, or stabilize it. Each common foundation type uses one or more of those routes.
| Foundation type | How it deals with clay | Where it fits | Code sections |
|---|---|---|---|
| Spread and continuous footings | Bears near the surface; usually paired with select fill or moisture-conditioned soil to limit swell | Light to moderate loads on low-swell or treated soil; minimum depth 12 in below undisturbed ground | §1806, §1809 |
| Post-tensioned slab-on-ground | Stiff slab designed to bend with predicted edge and center movement | Retail, offices, schools, light industrial where some movement is acceptable | §1808.6.2 (PTI DC10.5) |
| Conventionally reinforced slab with grade beams | Same idea, using rebar and the WRI/CRSI method | Where future slab cuts are likely or PT isn't preferred | §1808.6.2 (WRI/CRSI) |
| Drilled piers (drilled shafts) with grade beams and a structural or floating slab | Piers go below the active zone into stable clay or rock; beams and slab span or float above | Heavier frames, moisture-sensitive buildings, high swell estimates | §1808.6.1, §1810 |
| Mat foundation | One thick reinforced slab under the whole footprint | Heavy loads, closely spaced columns, or weak soil | §1808.6, §1809 |
| Driven piles | Steel or concrete piles driven to capacity | Deep soft soils or where drilling is impractical | §1810 |
The geotechnical report usually narrows the field to two or three options. The final call weighs cost, schedule, how much floor movement the use can accept (a warehouse with racking tolerates less than a church fellowship hall) and future plumbing or renovation. Our separate articles go deeper on spread footings, post-tension slabs on expansive soil and drilled pier foundations.
Once the type is chosen, the structural engineer checks that the foundation carries the loads without overstressing the soil or the concrete. For shallow foundations, the FHWA Soils and Foundations Reference Manual treats bearing capacity and settlement as separate checks, and settlement often ends up governing the size. For deep foundations, pier or pile capacity comes from the side friction and end bearing values in the geotechnical report, and the engineer also checks uplift, lateral load and the grade beams that span between piers.
On clay, the engineer also designs for movement:
Chapter 17 of the IBC lists the inspections that apply to foundations. Table 1705.6 covers soils: periodic checks that the excavation reaches proper material and depth, and continuous inspection while controlled fill is placed and compacted. Section 1705.7 requires continuous inspection of driven deep foundations, and §1705.8 requires continuous inspection of cast-in-place deep foundations such as drilled piers, including location, plumbness, diameter, length, embedment and concrete volume.
Under §1704.2, the owner or the owner's agent hires the special inspection agency, not the contractor. Budget for it separately.
Send the engineers:
Check before concrete:
Isbell Engineering Consultants is a structural, geotechnical and civil engineering firm based in Valley View, Texas. On the geotechnical side, its geotechnical engineering services include site investigations, soil and rock mechanics analysis and foundation recommendations for shallow foundations (spread footings, mat foundations) and deep foundations (piles, drilled shafts, caissons). On the structural side, its structural engineering services include foundation design, coordination with the geotechnical work and construction phase services. If you have a commercial, industrial or municipal project and want the soils work and foundation design pointed in the same direction from the start, send the project details through the contact page.
It's the engineering that sizes and details the part of a building that transfers its loads into the ground. It combines a geotechnical investigation of the soil and rock with structural design of the footings, slabs, piers or piles, and it ends in sealed drawings that the contractor builds from.
Shallow foundations bear near the surface: spread and continuous footings, slabs-on-ground and mat foundations. Deep foundations carry loads down to stronger or more stable layers: drilled piers (drilled shafts), caissons and driven piles. On expansive clay, a common commercial choice is drilled piers with grade beams, or a post-tensioned slab where some movement is acceptable.
Both. The geotechnical engineer investigates the ground and recommends foundation types, bearing pressures, settlement, swell and pier depths. The structural engineer uses those values to design and detail the foundation elements and seals the foundation drawings.
For most commercial buildings, yes. The IBC's presumptive bearing value for clay is only 1,500 psf, and anything higher needs a geotechnical investigation. Expansive clay also has to be identified and designed for under IBC §1808.6. Your local building department may require a report regardless, so check with them.
It depends on the project. The geotechnical field work, lab testing and report usually come first, then the structural design follows the building design. Ordering the geotechnical investigation early keeps it off the critical path.